Single-source risk at BOM level: find the parts that can stop your machines

A supplier list tells you who you buy from. Only the BOM tells you which machines stop if one of them fails. A 5-step method to map single-source exposure, with SAP tables and a scoring formula.

Not ready to talk yet? Take the 3-minute Procurement Data Check

IllustrativeAPPROVED SUPPLIERS PER PART46%1 supplier31%2 suppliers23%3+ suppliersSingle sourceone failure stops the line

TL;DR

  • A supplier list tells you who you buy from. Only the BOM tells you which machines stop if one of them fails.
  • Single source = one supplier in use today. Sole source = only one supplier exists. They need different fixes.
  • Explode the multi-level BOM, map each purchased part to its suppliers, and roll exposure up to machines, spare parts and customers.
  • End with a ranked short list. A heat map of 5,000 parts helps nobody.
For:CPO & category managersSupply chain planningEngineeringService parts planning

Single source, sole source, dual source: what’s the difference?

TypeMeaningTypical exampleTypical fix
Single sourceOthers could make it, you only use one supplierMachined bracket, sheet metal partQualify a second supplier
Sole sourceOnly one supplier existsProprietary control board, patented valveBuffer stock, last-time buy, redesign
Dual / multi sourceTwo or more approved suppliers in useStandard fasteners, ISO-size bearingsWatch price and quality
Design-lockedDrawing names one manufacturer part numberSpecific sensor or drive on the drawingEngineering change to allow equivalents

Why isn’t a supplier risk rating enough?

Supplier risk tools rate suppliers: credit score, country, delivery performance. Useful, but they miss the question that matters on the shop floor. A supplier with $40k of annual spend can still stop a machine that sells for $400k.

Supplier D1 site · 18 wk lead timeC-201Control boardControl cabinet AControl cabinet BRetrofit kit R2Machine type 500 · 60/yrMachine type 700 · 50/yrMachine type 900 · 30/yrSpare parts · 1,200 machines in fieldExposure next 12 months: $8.4MIllustrative example
Where-used view from one purchased part up to machines and the installed base.

The link between supplier and revenue runs through the BOM. That is why the analysis has to start there.

How do you map single-source exposure? 5 steps

  1. Explode the BOMs. Multi-level explosion of every active machine type, down to purchased parts. In SAP: tables MAST, STKO and STPO, or transactions CS12 (multi-level) and CS15 (where-used).
  2. Map parts to suppliers. Source list (EORD), purchasing info records (EINA / EINE) and actual purchase orders of the last 24 months (EKKO / EKPO). The source list says who is allowed. The purchase orders say who you really use.
  3. Classify. Single, sole, multi or design-locked. Engineering has to confirm sole-source and design-locked parts. Purchasing alone can’t tell.
  4. Roll up exposure. For each part: machines in the order book and forecast that use it, spare-part demand from the installed base, and contribution margin.
  5. Add likelihood. Supplier financial health, location, lead time, capacity and past delivery performance.

Scoring formula

Exposure ($, next 12 months) =
  Σ machine types using the part × planned units × contribution margin per unit
+ spare-part revenue of the part and its parent assemblies

Priority = Exposure × likelihood score (1–5) ÷ (weeks of stock cover + 1)

What does the output look like?

PartTypeSupplierMachines affectedExposureAction
C-201 Control boardSoleSupplier D, 1 site3 types, 140 units / yr$8.4MLast-time buy, redesign study
F-118 Hydraulic blockSingleSupplier K2 types$3.1MQualify second source
A-102 Linear guideDesign-lockedBrand on drawing4 types$2.7MECN to allow equivalents
S-077 Cast housingSingleSupplier P, owns the pattern1 type$1.9MSecure tooling ownership

Illustrative example.

Often overlooked: tooling

If the supplier owns the mould or the casting pattern, a second source is months away, not weeks. Check who owns the tooling before you mark a part as “single source, easy to fix”.

How do you keep it current?

  • Refresh monthly from ERP exports. It doesn’t need a new system.
  • Check every ECN that adds a purchased part: does it come with a second source?
  • Tie the top risks to inventory policy: safety stock or a last-time buy where a second source isn’t realistic.
  • Review the short list in the monthly S&OP meeting, not in a separate risk workshop.

Checklist: what data do you need?

  • Multi-level BOMs of all active machine types
  • Source lists and purchasing info records
  • 24 months of purchase order history
  • Order book and forecast per machine type
  • Spare-part demand per part from the installed base

FAQ

What is single-source risk?

Single-source risk is the risk that a part bought from only one supplier can’t be delivered, which stops production or service. It is measured by the revenue and machines that depend on that part.

What is the difference between single source and sole source?

Single source means you use one supplier although others could deliver. Sole source means only one supplier exists, often because of patents, proprietary design or tooling.

Why analyse supplier risk at BOM level?

Because a supplier with tiny spend can still stop your most profitable machine. Only the BOM shows which machines, spare parts and customers depend on each purchased part.

Which SAP data do we need?

Multi-level BOMs (MAST, STKO, STPO), source lists (EORD), purchasing info records (EINA, EINE), purchase orders (EKKO, EKPO) and the order book or demand plan for volumes.

How often should the analysis be updated?

Monthly is enough for most machine builders, plus a check whenever an engineering change introduces a new purchased part.